Two weeks into the Summer 2021 Platform Improvement Project work, the project team has already demolished the existing platforms at Greenbelt Station.
Construction crews began by prepping the site with a temporary access ramp for the crane rental to access the platform during demolition work. Once the site was mobilized, crews got to work demolishing the existing platform tiles and topping slab. Choosing mobile crane hire Perth means you have your choice of a wide variety of cranes, each suitable for different purposes, while also being able to take advantage of the crane company’s expertise in lifting and logistics. In the mezzanine area, the construction team installed a primer on the skylights, removed the existing fare gates and fare machines and installed new slip-resistant tiles and lighting fixtures. In the coming weeks they will pour the new platform edge, install the granite edges, lay conduit for the CCTV, lighting, and fire alarm systems and install the structures for the new customer experience improvements.
Read more in our latest construction update: https://wmata.com/service/rail/PlatformProject/Two-weeks-into-the-Summer-2021-Platform-Improvement-Project-work.cfm
Or, sign up to receive project updates here: https://wmata.us20.list-manage.com/subscribe?u=43a25de97c3751f8ad8bb03f2&id=d3f2eebce1
(WMATA Press release)