A proposed sidewalk along Branchville Road and 51st Avenue would help close an important gap in College Park’s pedestrian network, providing a more connected walking route toward the Greenbelt Metro Station.
At its Tuesday, October 6 meeting, the City Council will consider approving a $129,410 engineering design contract with Charles P. Johnson and Associates. The project would connect University Boulevard with the recently completed sidewalk along 52nd Avenue, helping complete the pedestrian route between University Boulevard and the Metro station.
A Longstanding Sidewalk Priority
The City identified this corridor as a priority through its 2018 sidewalk assessment, which evaluated projects supporting College Park’s Complete and Green Streets initiatives. Filling this gap would make it easier for residents to walk through the neighborhood and reach public transportation.
The proposed sidewalk would be approximately five feet wide. Its final alignment would be developed with community input, allowing residents to help shape the project as engineering work moves forward.
What the Design Contract Would Cover
The proposed contract includes surveying, evaluating sidewalk alternatives, reviewing utility and right-of-way impacts, preparing drainage plans, and developing construction documents and cost estimates.
It also includes two community meetings and up to two Council presentations, providing opportunities for residents and elected officials to review the design.
The City received proposals from three engineering consultants. Charles P. Johnson and Associates submitted the lowest proposed cost, and staff recommends approving its task order.
Funding and Next Steps
The $129,410 design contract would be funded through the City’s FY2027 Complete and Green Streets capital improvement budget. Approval would advance the engineering phase; it would not authorize sidewalk construction.
Staff anticipates approximately one year for design and permitting. However, the consultant’s proposal excludes permit applications, permit fees, construction administration, and certain other services, which could require separate authorization. Construction costs and a construction schedule would be determined as the project develops.
Residents are welcome to follow the discussion at 7:30 p.m. on Tuesday, October 6, in the second-floor Council Chambers at City Hall, 7401 Baltimore Avenue, or through Zoom. Written comments may be sent to cpmc@collegeparkmd.gov by 5 p.m. on the meeting day.