City’s Planning Department has given the following update of he Hollywood Gateway Park construction peoject.
  • The pavilion and ramp foundation walls have been completed
  • Sitework related to utility installation (water, electric and storm drain) is getting underway.
  • Next week, the maintenance of traffic plan along Edgewood Road will be implemented so that demolition of the existing curb and sidewalk and installation of new can begin.
  • Shop drawings for the pavilion have been approved and offsite fabrication will begin soon.

An early October completion date is anticipated. I’ll keep you posted as the project approaches completion.