KabirCares.org

City to Seek Funds for Hollywood Streetscape Project

At tonight’s Council meeting, the Council will consider sending a request for a State Bond bill for $200,000 in capital funding for the Hollywood Streetscape project. The estimated total capital cost of the project exceeds $1 million.

The City would like to proceed in phases, first with the streetscape phase of the plan, at an estimated cost of $106,000 for design and $425,000 for construction ($531,000 total). City funds would pay for $331,000 of the cost, and the State bond bill would provide the remaining $200,000.

If funded, the construction will happen in phases. We’re working on the first phase only at this time. The scope includes the pavement, roadway & landscaping improvements itemized in the conceptual plan (please see below in the link)

Final Design: March 2016 – August 2016
Permits: September 2016 – November 2016
Advertise for Bids: December 2016 – February 2017
Construction: April 2017 – July 2017