Berwyn Pedestrian Bridge Replacement to Start on November 21

  WMATA is planning a Green Line shutdown from College Park to Greenbelt for the weekend of Nov. 21-22 for the contractor to install the replacement span of the bridge.
  • The crane should arrive Nov. 18.
  • The bridge span should arrive on site Nov. 19 or 20.
  • The contractor is working with adjacent property owners, particularly those in the vicinity of the crane.
 
Following installation of the replacement span, it could take another two weeks to finish preparing the bridge for public use. 
Berwyn Heights will be using “early December” in their communications to the public. 
Delays could occur due to bad weather or other unforeseen issues. 
 